|
DB 16 Spreads its New Wings
By: Will Wilson, PMP, Project Manager
Jim Bass, Project Engineer
Western Hemisphere Operations
The offshore construction activity supporting the energy industry
in the Gulf of Mexico and around the world is increasingly moving
into deeper and deeper water depths. In response to this trend,
JRM upgraded the dynamically positioned (DP) Derrick Barge 16 with
a modular S-lay package, enhanced deepwater lowering system, and
automatic welding equipment suite. The DB-16 recently completed
the offshore installation of the Conger subsea pipeline system for
the Conger partners Amerada Hess, Shell, and Kerr McGee in the Gulf
of Mexico.
The Conger flowlines "tie-back" or connect
the Conger development of subsea wells in Garden Banks Block 215
to Shell's Salsa Offshore Platform in Garden Banks Block 172. Water
depths vary from 1450' at the Conger site to 700' at the Salsa platform.
Production from the wells will flow to the platform
via dual, 8 inch diameter, insulated flowlines (4.5 miles in length
each) connected to a subsea manifold by flowline jumpers. An additional
well is tied into the subsea manifold via a one-mile long, 6 inch
diameter insulated flowline. Product will flow through an existing
pipeline network to shore-based facilities. The dual 8" flowlines
allow "round trip" pigging of the system from the Salsa
platform.
The
project is technically noteworthy in that the design maximum allowable
operating pressure of the flowline system is 13,600 psi. This pipeline
system is the first "15 K" subsea pipeline system in the
world. JRM was responsible for installing the three flowlines, four
pipeline end manifolds, and the subsea distribution manifold. The
flowlines were connected to the Salsa platform by pulling the starting
ends of the pipelines through existing J-tubes at the Salsa platform.
JRM's scope was completed with the successful hydrotest. Additionally,
JRM's Mentor Engineering designed the pipeline end manifolds (plems)
with JRM subcontracting fabrication to Oil States Industries.
The work was performed under a blanket service agreement
with Shell, which allows JRM to be reimbursed for actual project
costs and an agreed profit rate with a gainshare/painshare adjustment
based on comparison of actual project cost to an agreed upon target
cost.
The project was awarded to JRM in November 1999; Installation
was complete in July 2000 and hydro-testing was complete in September
2000. The project schedule, with completion coming less than a year
following award, highlights the accelerated pace now being applied
to deepwater installation work. Fortunately, the project team, and
vessel crew identified for the work had completed similar deepwater
work tasks involving JRM's DB-50 in the recent Shell King, Angus,
Macaroni, and Europa projects. The challenge was to apply the experience
and lessons from these projects to a newly configured deepwater
construction vessel without sacrificing JRM's commitment to Safety
and Quality.
The JRM installation project team was organized to
include representatives from Project Management, Marine Operations,
Mentor Engineering, and New Orleans Engineering. The organization
capitalized on the experience and relationships built on the previous
deepwater installations. The team members were familiar with the
procedures developed recently on past projects, the lessons learned
from execution, the customers for whom we were working, and the
interfaces typical to the required planning tasks.
The project team established interfaces with the team
responsible for the DB-16 upgrade to insure that the vessel would
be fit for purpose "right out of the box". Project requirements
and concerns were fed to the upgrade team, and schedule constraints,
concerns and conflicts were communicated by and between the project
team, the upgrade team, and Shell. Vessel trials were accomplished
upon completion of the upgrade work to validate vessel capabilities.
Shell and McDermott personnel, from Vice Presidents to new hire
craft labor, participated in a series of "technical limits"
workshops which worked to optimize every step of the actual offshore
installation and establish project goals which were achievable and
"owned" by those who could make them happen .
As
offshore projects go into deeper water using new technology, ownership
and project risk are increasingly being shared by the practice of
partnerships among energy companies. This practice requires that
the project team respond to the needs of a larger group of project
stake-holders. In the case of Conger, JRM was working directly for
Shell, while the operator of the development was Amerada Hess. Kerr
McGee also owned an interest. It was important to the success of
the project that all of the owners needs be met. In a partnering
arrangement it is important to adequately communicate with all stakeholders
and at the same time make the decision process in planning activities
meet the strict schedule constraints required in a fast track project.
In the case of Conger the lines of communication and authority were
well established and frequently used. Input from all quarters was
encouraged to insure that the best practices and plans were used,
but a firm "base case" was established as the governing
plan. New ideas and scenarios had to quickly show that they possessed
real merit with respect to safety, quality, and/or efficiency in
order justify a change in the base case.
The Conger project was completed with less than budgeted,
mechanical downtime, no lost time accidents, or builders risk events,
and with significant accomplishments towards the technical limit
goals set. The DB-16 demonstrated that it could efficiently perform
multi-faceted deepwater installations under a single mobilization.
JRM can expect there will be many more of these fast track, deepwater
tie-back projects in our future.
JRM now has a proven vessel in its fleet which can
efficiently execute all of the varied demands of deepwater projects
without the costly mobilization of multiple vessels, crews, and
subcontractors. The capabilities of the DB-16, coupled with the
deepwater construction experience of our people and the lesson's
learned on Conger, put us in a perfect position to capture and execute
more work in the growing deepwater market.
|