|
|
 |
|
Touring ATLANTIS, using QuicktimeVR
(You will need to install Apple's Quicktime
to view the QTVR panoramas.)
Morgan City
Yard
In this 360 degree panorama of the Morgan City Yard, all three
ATLANTIS modules can be seen.
ATLANTIS
Production Module (v1)
This 360 degree panorama captures a mid-level floor on the
Production Module giving viewers the illusion they are standing
in the center of the module.
ATLANTIS
Compression Module
In this 180 degree panorama, workers are seen on an upper
level of the Compression Module.
ATLANTIS
Production Module (v2)
This 345 degree panorama of the Production Module shows testing
and commissioning activities nearing completion.
ATLANTIS
Production Module (v3)
In this 360 degree panorama of the upper level of the Production
Module, interconnect piping and E/I installations are nearing
completion.
|
 |
|
ATLANTIS project background information
Discovered in May 1998, ATLANTIS is located in 4,500
to 6,800 feet of water in Southern Green Canyon in the Gulf
of Mexico. British Petroleum and BHP-Billiton jointly own
the project. Sanctioned in late 2002, the project is anticipated
to cost approximately $2 billion and is scheduled for first
oil production in the third quarter of 2006. ATLANTIS employs
the concept of a Production Quarters (PQ) platform supported
by a separate, dedicated Mobile Offshore Drilling Unit (MODU).
Nameplate facility throughput is 150 mboed, and up to 180
mmscfd of natural gas. Twenty wells are planned, which include
sixteen producers and four water injection wells. The Morgan
City, Louisiana J. Ray McDermott fabrication site constructed
the three topsides production modules. Daewoo in Okpo, Korea,
performed Hull fabrication for the PQ platform with integration
of the facilities occurring in Corpus Christi, Texas.
J. Ray McDermott's scope was to procure bulk steel and interconnect
piping materials and to assemble the three modules totaling
13,600 tons (6,700 tons of structural steel, 1,775 tons of
interconnect piping, 5,125 tons of engineered equipment).
Nearly 2.35 million man-hours were expended in our facility
from June 2003 through May 2005. J. Ray McDermott was responsible
for getting the facilities to mechanical completion and ready
for Client commissioning.
|

Morgan City Yard - 3 ATLANTIS Modules
|
|
ATLANTIS project background information
The Owners lead site representative summed up the ATLANTIS
accomplishment by describing the ATLANTIS topsides fabrication
as a success in every way that projects are measured:
- Schedule - we're hitting the completion dates that were
set over two years ago.
- Cost - we're going to end up within one percent of the
budget established in late 2003.
- HSE - Atlantis' construction safety performance is the
safest of all of BP's recent projects.
JRM believes that the keys to successful construction of
the ATLANTIS modules were:
- Excellent JRM constructability comments, acted on by the
owner and topsides designer.
- A comprehensive, required on site date, matrix of all
deliverables (drawings and owner furnished equipment) was
mutually agreed upon between JRM, the owner and the topsides
designer.
- Strong Project Controls; Planning & Scheduling, ConstructSim,
PIMS, and DTCMS
|

ATLANTIS Generation Module
|
|
Touring ATLANTIS: Panorama background information
These Morgan City, LA construction yard panorama
media tours were assembled from digital still images shot
in overlapping sequence while panning across the modules'
environments. Downloaded and imaged-processed in Adobe PhotoShop,
the 10, 12 or 15 shots (depending on the pan range of the
tour) were then stitched into QTVR (Quicktime Virtual Reality)
panoramas using Apple VR authoring software.
Truly user-controlled, interactive experiences, QTVR panoramas
not only enable viewers to see an environment but to actively
explore it by scrolling and zooming around in it in real time
with the mouse button and or keyboard.
Photographed in April 2005, by San Francisco environmental
photographer, Bram Druckman, the three ATLANTIS topsides modules
were only weeks away from being completed and turned over
to BP for their use offshore in the Gulf of Mexico. Of his
experience photographing atop the modules, Bram was not only
impressed by their massive size but was doubly impressed by
the attention played to safety by everyone on the construction
site.
|

Morgan City Yard - 3 ATLANTIS Modules
|
Challenging Projects. It's What We Do
|
 |