Company Profile
Company Charter
Code of Conduct
Press Room
Investor Relations
Newsletters
Health, Safety & Environment
Library
Guest Book
Links

Project Management
Engineering
Fabrication
Marine Installation
SubSea
 

JRM Engineering
Mentor Subsea
FloaTEC

Map

Altamira, Mexico
Baku, Azerbaijan
Batam Island, Indonesia
Dubai, UAE
Houston, Texas
Jakarta, Indonesia
Morgan City, Louisiana
New Orleans, Louisiana

Our Philosophy
Employment Opportunities

Supplier Registration

Site Map

CompanyServicesTechnologyProjectsLocationsHuman ResourcesSuppliersContact Us Search
 
Home > Projects

ARCO 52A TRIPOD

Drilling & Production Platform

 
Client Arco Oil & Gas Co.
Region Gulf of Mexico
Location South Pass 52
Water Depth 533 ft.
Services Performed Procurement, Front-End Engineering Design, Detailed Engineering
Contractor J. Ray McDermott, Inc.
Award Date 1989
Completion Date 1992
Production Capacity 65 mmscfd

Scope:

  • JRME provided detailed engineering and procurement assistance for this drilling and gas production tripod.
  • The platform was installed in 545' of water (a record, at the time of installation, for a drilling/production tripod).
  • Facilities were designed to process 60 mmscfd of gas.
  • JRME also developed bid packages for fabrication, transportation, and installation.

Description:

  • 6 wells, 1 rig, 3-leg jacket, 3 - 72"Ø skirt piles, production module

Technology:

  • JRME performed detailed design of the overall control system for an unmanned offshore platform in the Gulf of Mexico that included an RTU system. The RTU and platform control system was designed to monitor platform performance, provide emergency shutdown, and provide for remote shutdown and remote startup of selected process equipment. Communication from the RTU to the central control system is via a radio communication system. RTU input/output count was approximately 305 total points.
  • JRME prepared the control system design, design specifications, inquiry requisitions, purchase specifications, and purchase requisitions; performed technical and commercial supplier quotation evaluations and factory acceptance tests; selected/recommended supplier selection; and reviewed certified supplier documentation.