Client
|
BP Exploration
|
|
Region
|
Gulf of Mexico
|
|
Location
|
Canyon 699, 700, 742 & 744
|
|
Water Depth
|
4400-7100 ft.
|
|
Services Performed
|
Fabrication
|
| Contractor |
J. Ray McDermott,
Inc. |
| Award |
November, 2000 |
| Completion |
2005 |
| Partners |
BHP Billiton |
| Project
Manager |
Denis Webre |
| Key
Participants |
Mustang Engineering
- major subcontractors not yet selected |
| Prod.
Capacity |
150 mbopd
180 mmscfd gas |
Scope/Description:
- The Atlantis topsides consist of three modules, the Production
and Compression Modules, each weighing about 5,000 tons,
and a Generation Module weighing 4,000 tons. Equipment consists
of electrical generating equipment and oil and gas processing
equipment. The three modules will be installed on a moored
semi-submersible hull.
|

Innovations:
- Atlantis is one of four major BP deepwater projects for
the Gulf of Mexico under construction at the company’s
Morgan City facility which is under exclusive use for BP.
|