Client
|
Amoco
|
|
Region
|
Caspian Sea
|
|
Location
|
Azerbaijan
|
|
Water Depth
|
480-500 ft.
|
|
Services Performed
|
Front-End Engineering Design, Detailed Engineering
|
| Contractor |
McDermott Marine Construction (now J. Ray McDermott, Inc.) |
| Award date |
1991 |
| Completion date |
1992 |
| Project Mgr. |
Bill Mahler |
| Customer Partners |
Azerbaijan Oil Company
British Petroleum |
| Key Participants |
Williams Bros. - onshore pipeline |
| Prod. Capacity |
360,000 BPD Oil
200,000 BPD Water
480 Mmscfd Gas |
Description:
- Four wellhead platforms, two production platforms, subsea pipelines connecting wellhead to production platforms and production platforms to onshore facilities
Scope:
- Lump sum contract for the feasibility study for the development of the Azeri field in the Caspian Sea. Develop conceptual design for offshore and onshore facilities and cost estimates for the required facilities.
|
Technology:
- Offshore wells, production separators, gas turbine driven oil shipping pumps and gas compressors
- Gas dehydration with TEG
- Seawater deaeration and injection facilities for water flood
- Necessary utility systems such as flare, drain, power generation, etc.
- Onshore oil dewatering/desalting/ stabilization, crude oil topping unit for diesel fuel production
- Gas dewpoint control system
- Crude oil storage facilities
- Produced water treating and disposal
|