Client
|
BP Migas
|
|
Region
|
Asia Pacific
|
|
Location
|
Belanak Field, South Natuna, Indonesia
|
|
Water Depth
|
295 ft.
|
|
Services Performed
|
Procurement, Fabrication
|
| Contractor |
P.T. McDermott
Indonesia |
| Award |
August, 2001 |
| Completion |
May, 2004 (scheduled) |
| Yard/Marine
Base |
Batam Island,
Indonesia |
| |
|
| Customer
Shareholders |
ConocoPhillips
Indonesia
PT Brown & Root |
| Total
Weight |
28,085 ST |
Scope:
- Lump sum contract for the bulk procurement, construction,
integration and at shore commissioning assistance of topside
modules for a floating production, storage, and offloading
(FPSO) vessel comprising 13 different process modules and
a 120-man living quarters.
- The FPSO was designed to process up to 500 million cubic
feet gas per day for export, up to 100,000 barrels of oil
and condensate per day, and up to 24,140 barrels of LPG
per day. The 935ft long vessel will store up to one million
barrels of oil.
|
Description:
- Bulk Procurement, Construction, Integration and Commissioning
Assistance
|