Company Profile
Company Charter
Code of Conduct
Press Room
Investor Relations
Newsletters
Health, Safety & Environment
Library
Guest Book
Links

Project Management
Engineering
Fabrication
Marine Installation
SubSea
 

JRM Engineering
Mentor Subsea
FloaTEC

Map

Altamira, Mexico
Baku, Azerbaijan
Batam Island, Indonesia
Dubai, UAE
Houston, Texas
Jakarta, Indonesia
Morgan City, Louisiana
New Orleans, Louisiana

Our Philosophy
Employment Opportunities

Supplier Registration

Site Map

CompanyServicesTechnologyProjectsLocationsHuman ResourcesSuppliersContact Us Search
 
Home > Projects

BELANAK WELLHEAD AND PIPELINES

EPCI

 
Client BP Migas
Region Asia Pacific
Location Indonesia
Water Depth 295 ft.
Pipeline(s)
  • 24" x 60 mi. gas export
Services Performed Procurement, Detailed Engineering, Fabrication, Subsea, Pipelines, Marine Installation
Contractor P.T. McDermott Indonesia
Award July, 2001
Completion August, 2003 (scheduled)
Yard/Marine Base

Batam Island, Indonesia

Total Weight 18,700 ST
Customer Shareholders ConocoPhillips Indonesia
   

Description:

  • Engineering, Procurement, Construction, Offshore Installation (EPCI), and mechanical completion

Scope:

  • Lump sum contract for the engineering, procurement, construction, offshore installation of two wellhead platforms, flowlines and pipeline end manifolds (PLEMs), an oil-offloading buoy and a 60-mile 24"gas export pipeline
  • In-field pipelines will connect each platform and the oil-offloading buoy to the FPSO. The FPSO gas export PLEM will contain connection points for the gas export line and a tie-in for future regional developments, and the 24" pipeline will connect the FPSO to a PLEM on the Duyong gas line
  • Total weight of each wellhead platform: 2,200ST (jacket) and 3,000ST (integrated deck)