Client
|
Foster Wheeler Eastern Limited
|
|
Region
|
Spulau Ayer Chawan
|
|
Location
|
Singapore
|
|
Services Performed
|
Fabrication
|
| Contractor |
Foster Wheeler
Eastern Limited |
| Award |
January, 1995 |
| Completion |
May, 1996 |
| Yard/Marine
Base |
Batam Island,
Indonesia |
| Total
Weight |
19,290 ST |
Description:
|
Scope:
- Unit rate contract for detailed engineering, partial procurement,
fabrication and outfitting of 99 modules for an onshore
aromatics plant comprising of 50 pipe racks (PAR's), 34
pre-assembled units (PAU's) and 15 dressed vessels (VAU's).
Modules were fabricated in a pre-determined order to meet
the 21 shipments necessary to meet the plant erection sequence.
|