|
Client
|
Shell Exploration & Production Company
|
|
Region
|
Gulf of Mexico
|
|
Location
|
Garden Banks 341, 384, 427 & 426
|
|
Water Depth
|
2000-2860 ft.
|
|
Pipeline(s)
|
- 10" x 11 mi. 2 PIP
- 6" x 11 mi. 2
|
|
Services Performed
|
Detailed Engineering, Subsea, Pipelines, Marine Installation
|
| Contractor |
J. Ray McDermott,
Inc. |
| Award |
November, 2002 |
| Completion |
November, 2003 |
| Project
Managers |
Scott Springman
/ Hassan Dehaini |
| Key
Participants |
Bayou Pipe
Coating - Quad Joint Fabrication
Shaw Pipeline Services - Aut. U.T. Inspection
Fugro Chance - Surface & Acoustic Positioning
Oceaneering - ROV Services
Max Welders - PL Sled Fab. |
| Prod.
Capacity |
22,000 bopd
75 mmscfd |
Description:
- Two (2) subsea wells located in Garden Banks 341 providing
gas/condensate production to the Shell Auger TLP via two
(2) individual 10x6 electrically heated pipe-in-pipe flowlines
and two (2) wet-insulated 6” steel catenary risers.
- The dual subsea flowlines tie-back to Auger approximately
11.0 miles away, creating the fourth subsea development
to tie-back to Auger.
- Peak production is expected to reach 22,000 barrels of
oil/gas condensate and 75 million cubic feet of gas per
day.
Technology:
- Installation of a pipe-in-pipe (PIP) flowline system without
the use of steel pipe bulkheads. Specialized installation
procedures and tooling were utilized allowing the outer
casing pipe to slide unimpeded over the inner casing pipe
during offshore welding and installation operations.
- Installation of water stop seals and other installation
procedures employed to eliminate moisture of any kind entering
the PIP flowline annulus during offshore installation operations.
- Electrical testing of every PIP quad joint prior to and
subsequent to offshore welding and AUT inspection activities.
- Installation of the world’s first subsea Mid-Line
Electrical Connector Assembly for an electrically-heated
PIP Flowline System.
- Use of specially designed SCR Installation Mast for SCR
transfer operations between the DB50 and the Auger TLP.
|
Scope:
- Installation contract for the construction of two (2)
electrically-heated pipe-in-pipe (PIP) flowlines comprised
of 6.625” x 0.719” API 5L X70 SMLS carrier pipe
and 10.750” x 0.438” API 5L X70 ERW casing pipe.
The 6.625” carrier pipe was insulated with 1.3-inch
thick jacketed polyurethane foam.
- Flowline construction activities included the installation
of two (2) PIP flowline initiation sleds located in 2,000
feet of water using pre-installed suction piles located
adjacent to the two (2) subsea wells, and the installation
of two (2) 6.625” x 0.844” API 5L X70 SMLS steel
catenary risers (SCR’s) located in 2,860 feet of water
and insulated with 3.0” of multi-layered Thermotite
insulation.
- Installation engineering work was performed by JRM Engineering
in Houston, TX. All flowline installation activities were
performed by the Derrick Barge No. 50 (DB50) utilizing J-Lay
installation methods. All welding work was performed by
the JRM Vermatt Bug-N-Band Automatic Welding System (JBBS).
Innovations:
- Subsea Mid-Line Electrical Connector Assembly For
Hydrate Mitigation
- Purpose-Built SCR Installation Mast Eliminating Need
For Drill Rig Assistance During SCR Pull-In Operations
|