Company Profile
Company Charter
Code of Conduct
Press Room
Investor Relations
Newsletters
Health, Safety & Environment
Library
Guest Book
Links

Project Management
Engineering
Fabrication
Marine Installation
SubSea
 

JRM Engineering
Mentor Subsea
FloaTEC

Map

Altamira, Mexico
Baku, Azerbaijan
Batam Island, Indonesia
Dubai, UAE
Houston, Texas
Jakarta, Indonesia
Morgan City, Louisiana
New Orleans, Louisiana

Our Philosophy
Employment Opportunities

Supplier Registration

Site Map

CompanyServicesTechnologyProjectsLocationsHuman ResourcesSuppliersContact Us Search
 
Home > Projects

HUIZHOU 26-1

Field Development

 
Client ACT Operators Group
Region China
Location Huizhou Field
Water Depth 121-364 ft.
Pipeline(s)
  • 12" x 31.85 mi. infield
  • 6" x 31.85 mi. infield
Services Performed Procurement, Detailed Engineering, Fabrication, Pipelines, Marine Installation
Contractor P.T. McDermott, Inc.
Award June, 1989
Completion July, 1991
Yard/Marine Base Batam Island, Indonesia
Total Weight 19,508 ST

Description:

  • Engineering, procurement, construction, offshore installation (EPCI)

Scope:

  • Lump sum contract for the engineering, procurement, construction, and offshore installation and pre commissioning of an eight-pile self contained drilling/ production platform. Comprising an eight-leg jacket topsides workover drilling unit, gas lift compressor module, water injection package, 50-man living quarters module, low flow pipeline start-up heater package, water treatment facility (CPI/DGF), four gas turbine driver generator sets and associated in-field pipelines.