Client
|
Mobil Exploration Indonesia, Inc.
|
|
Region
|
Indonesia
|
|
Location
|
Offshore North East of Sumatra
|
|
Water Depth
|
354 ft.
|
|
Pipeline(s)
|
- 30" x 63.24 mi. Gas Transmission
|
|
Services Performed
|
Procurement, Detailed Engineering, Fabrication, Pipelines, Marine Installation
|
| Contractor |
P.T. McDermott
Indonesia |
| Award |
February, 1997 |
| Completion |
May, 1999 |
| Yard/Marine
Base |
Batam Island,
Indonesia |
| Total
Weight |
9,480 ST (deck,
jacket and piles) |
Description:
- Engineering, procurement, construction, offshore installation
(EPCI)
|
Scope:
- Lump sum contract for the engineering, procurement, construction,
and offshore installation, and pre commissioning of a gas
treatment platform and a gas transmission pipeline, from
the NSO platform to an onshore liquefied natural gas (LNG)
facility. Platform was a four-pile jacket with 72”
diameter skirt piles.
Innovations:
- At the time of the platform’s installation, it was
the deepest facility in Indonesia.
|