Client
|
Boskalis Westminster B.V.
|
|
Region
|
Caspian Sea
|
|
Location
|
Kazakhstan
|
|
Water Depth
|
13-26 ft.
|
|
Services Performed
|
Marine Installation
|
| Contractor |
J. Ray McDermott
Middle East, Inc. |
| Award |
July, 1998 |
| Completion |
October, 1998 |
| Water Depth |
13 and 26 Feet (two sites) |
| Yard/Marine
Base |
Baku, Azerbaijan
and Jebel Ali, Dubai, United Arab Emirates |
Description:
|
Scope:
- Lump sum contract to supply 48 piles of 63” diameter,
2.4” thick and 98ft long; mobilization of marine equipment
and installation of 26 piles to a depth of 66ft at two sites.
Innovation:
- First of a kind. The first offshore piling project undertaken
by J. Ray in the North Caspian Sea - it had to be completed
before the onset of the winter, as the piles were required
to protect the world’s largest posted drilling barge
from winter ice flows.
|