Client
|
Shell Deepwater Development
|
|
Region
|
Gulf of Mexico
|
|
Location
|
Viosca Knoll 912
|
|
Water Depth
|
3214 ft.
|
|
Pipeline(s)
|
- 12" x 30 mi. oil
- 14" x 23 mi. gas
|
|
Services Performed
|
Fabrication
|
| Contractor |
J. Ray McDermott, Inc. |
| Award |
January, 1995 |
| Completion |
December, 1996 |
| Project Managers |
Rick Johnson
Denis Webre |
| Key Participants |
Bay, Inc. - Piping
Seco Industries - Elec./Inst.
Broadmoor - Architectural
Sipco - Fireproofing |
| Prod. Capacity |
60,000 b/d Oil
200 mmcfd Gas |
| Reserves |
250 mmbbs Oil Equivalent |
Innovations:
- Construction managed by Integrated Site Team
Description:
- Tension leg platform consisting of 5 modules weighing a total
of approx. 11,000 tons, which was built in Morgan City fabrication
yard
|
Scope:
- Risk sharing / reimbursable contract, with J. Ray McDermott
being responsible for fabrication of TLP topsides
|