Client
|
Shell Deepwater Development
|
|
Region
|
Gulf of Mexico
|
|
Location
|
Mississippi Canyon 810 "A"
|
|
Water Depth
|
4000 ft.
|
|
Pipeline(s)
|
|
|
Services Performed
|
Fabrication, Pipelines
|
| Contractor |
J. Ray McDermott, Inc. |
| Award |
July, 1996 |
| Completion |
July, 1998 |
| Project Managers |
Rick Johnson
Jim Szush |
| Customer Partners |
BP Exploration, Inc.
Exxon Co., USA
Conoco |
| Key Participants |
Bay, Inc. - Piping
Seco Industries - Elec./Inst.
Broadmoor - Architectural
Sipco - Fireproofing |
| Prod. Capacity |
150,000 b/d (Oil)
400 mmcfd (Gas) |
| Reserves |
400 mmbbs Oil Equivalent |
|
Description:
- Tension leg platform consisting of 6 modules weighing a total
of approx. 18,000 tons, which was built in Morgan City fabrication
yard.
Scope:
- Risk sharing / reimbursable contract with J. Ray McDermott
responsible for fabrication of TLP topsides.
Innovations:
- Construction managed by Integrated Site Team
|