Client
|
Azerbaijan International Operating company
|
|
Region
|
Caspian Sea
|
|
Location
|
ACG Field
|
|
Water Depth
|
430 ft.
|
|
Services Performed
|
Fabrication
|
| Contractor |
Azerbaijan International
Operationg Company |
| Award |
October, 2002 |
| Completion |
West Azeri - November, 2005
(scheduled)
East Azeri - September, 2006 (scheduled) |
| Yard/Marine
Base |
Baku Deepwater Jacket
Factory, Baku, Azerbaijan |
| Total Weight
|
34,172 ST |
|
|
Description:
- Fabrication, assembly, hookup and commissioning
|
Scope:
- Lump sum contract for the fabrication, assembly, hook-up
and commissioning of two integrated topside decks, West
Azeri (WA) and East Azeri (EA), each weighing approximately
17,085ST.
- The two decks will support drilling facilities, living
quarters, power generation and other process equipment and
facilities.
- Fabrication work will be done primarily in Azerbaijan
utilizing the infrastructure, equipment and labor of SOCAR’s
Baku Deep Water Jacket Factory (BDJF) fabrication facility
in Baku.
- As part of its Topsides Fabrication contracts with AIOC,
MCCI has established a full project infrastructure at the
BDJF yard including a comprehensive upgrade program of the
existing facilities.
|