Client
|
Conoco Indonesia Inc. Ltd.
|
|
Region
|
Middle East
|
|
Location
|
Indonesia
|
|
Water Depth
|
290 ft.
|
|
Services Performed
|
Procurement, Detailed Engineering, Fabrication, Subsea, Pipelines, Marine Installation
|
| Contractor |
P.T. McDermott
Indonesia |
| Award |
May, 1999 |
| Completion |
March, 2001 |
Customer
Shareholders |
Premier Oil Natuna Sea
Limited
Gulf Indonesia Resources, Ltd. |
| Total Pipeline
Length |
416 miles of 28", 22",
16" and 14" |
|
|
Description:
- Engineering, procurement, construction, offshore installation
(EPCI)
|
Scope:
- Lump sum contract for the engineering, procurement, construction,
and offshore installation, de-watering, drying, testing,
commissioning and “gas up”, of a subsea pipeline
system to transport a daily average of 325 million cubic
feet of natural gas from the West Natuna fields to Singapore.
Innovation:
- Project was finished more than four months ahead of schedule
allowing “gas up” six months ahead of schedule.
Record pipelay rates were achieved.
|