Client
|
Murphy Exploration & Production Co.
|
|
Region
|
Gulf of Mexico
|
|
Location
|
Green Canyon 338
|
|
Water Depth
|
3330 ft.
|
|
Services Performed
|
Project Management, Procurement, Front-End Engineering Design, Detailed Engineering, Fabrication, Subsea, Marine Installation
|
| Contractor |
J. Ray McDermott,
Inc. |
| Award |
March, 2002 |
| Completion |
April, 2004 |
| Partners |
Spinnaker
Exploration Co.
Dominion Exp. & Prod., Inc. |
| Project
Manager |
Ian Cochran |
| Key
Participants |
Project Management
- SparTEC, Inc.
Engineering - JRM Engineering
Riser Design - Mentor Subsea Tech & 2H Offshore, Inc.
Hull Fab & Transport - JRM Middle East, Inc. &
Fairmount Marine B.V.
Topsides Fab - TNG, S.A. & Gulf Island, LLC.
ITR Air Can Fab - Kellogg B&R, Inc.
Installation - JRM Marine |
| Total Weight |
14,093 ST (hull only) |
| Prod.
Capacity |
110 MMscfd
Gas
60 Mbpd Oil |
Scope/Description:
- Project Management
- Engineering & Procurement Management
- Hull, Mooring System & Topside detailed engineering
design
- Procurement of all topsides and hull marine systems equipment
and mooring system equipment and components
- Hull and topsides fabrication, assembly, outfitting and
pre-commissioning
- Installation, hook-up and commissioning ready for hydrocarbons
|

Innovation/Technology:
- Turnkey EPCI contract services
- Fast-track project schedule and delivery
- Topsides dual barge lift installation
- Dry trees, top tension risers
- Offset capability for MODU drilling
- Fatigue resistant buoyancy can system
- Fully supports completion and workover rigs
|